9690 - Lathe Installation
TED · 740092-2026Award noticeawardedNo deadline given
Value
Estimated€1,374,712 · 1,374,712.34 EUR
Awarded€1,374,712 · 1,374,712.34 EUR
WinnerCRS Contracts
Who already wins at this buyer
Firms with recorded awards from Iarnród Eireann-Irish Rail in this tender’s CPV categories — the incumbents you are bidding against.
| Firm | Wins | Awarded | Last win |
|---|---|---|---|
| TRIUR Construction Limited | 6 | €7,582,759 | 2026-10-22 |
| Global Rail Services Ltd | 5 | €3,366,759 | 2026-09-23 |
| Carra Plant Hire Ltd | 5 | €601,908 | 2026-09-16 |
| Pod-Trak infrastructure | 3 | €4,905,331 | 2026-07-20 |
| Kavanagh Crane Hire Ltd | 2 | €3,030,000 | 2026-09-16 |
Full buyer profile: what Iarnród Eireann-Irish Rail buys and who wins it →
CPV codes
45200000 Construction work45210000 Construction work45213200 Construction work45213250 Construction work45213320 Construction work45213321 Construction work45213340 Construction work45221122 Construction work45234100 Construction work45234114 Construction work45234115 Construction work45255120 Construction work45262410 Construction work45262690 Construction work45300000 Construction workDescription
This is a complex civil engineering and railway‑interface project to rebuild The Lathe Building at Drogheda Depot, construct a new lathe pit and supporting structures, install new utilities and track slab, and enable specialist equipment installation delivered under strict Irish Rail safety, possession, and environmental requirements.
Similar tenders
Closest by meaning — across languages, via embeddings.
| Published | Title | Buyer | Match |
|---|---|---|---|
| 2026-09-08 | 9096-77 (9915) UBC123C Precast Unit Installation Works | Iarnród Eireann-Irish Rail IE | 88% |
| 2026-07-08 | 9796- (9096-65) Masonry Repair and Repointing | Iarnród Eireann-Irish Rail IE | 87% |
| 2026-10-23 | 10072 - Sandblasting Maintenance and Equipment | Iarnród Eireann-Irish Rail IE | 87% |
| 2026-10-19 | 9853 (7774-44) DART Platform Accessibility: Phase 2 Construction Works | Iarnród Eireann-Irish Rail IE | 87% |
| 2026-07-21 | 9163 Single Supplier Framework Agreement for Design and Build Civil and Structural Contractor for DART+ | Iarnród Eireann-Irish Rail IE | 87% |
| 2026-06-19 | 9819 - Rock Cutting Stabilisation + Drainage Improvement Works CTB035D | Iarnród Eireann-Irish Rail IE | 87% |